6  Electrical Connection

Operating Manual

MC-BOX-12-3-20-BE-en-10

21

6.5 Connecting the Loads

The line conductors L1, L2 and L3 are routed via a fuse switch-disconnector in the Multicluster Box. The maximum

permitted 200 A LV/HRC size 1 fuse links are installed in the fuse switch-disconnector by default.

Cable requirements:

☐ Conductor material: copper
☐ Conductor cross-section: 120 mm² to 150 mm²
☐ The power cables must be ground-fault and short-circuit protected.

Procedure:

1. Insert the power cables into the Multicluster Box (see Section 9.3.1, page 31).
2. Connect the grounding conductor to the grounding busbar

(AF 17, torque: 15 Nm). To do this, use the screw terminal

included in the scope of delivery.

3. Connect the neutral conductor to the spring-cage terminal N at terminal X103:4 (see Section 9.4.1, page 34).
4. Connect the line conductors to the spring-cage terminals L1, L2 and L3 at terminal X103:1-3.
5. Ensure that a right-hand rotating magnetic field is present at the load terminal.
6. Provide for strain relief of the power cables by attaching them to the appropriate cable support rail. Use the strain

reliefs and counter-troughs provided.

7. According to the type of cable routing and the installation conditions, determine the required fuse link for the fuse

switch-disconnector and insert it into the fuse switch-disconnector Load.

Cable Protection
The Multicluster Box is not a substitute for the load distribution board. Between the Multicluster Box and the loads,

you must install a distribution board with circuit breakers to protect and isolate the loads, as well as a residual-current

device. Make sure all standards and directives applicable at the installation site are observed.