6  Electrical Connection

SMA Solar Technology AG

24

MC-BOX-12-3-20-BE-en-10

Operating Manual

6.9 Connecting the Control Cables

6.9.1 Assignment of Spring-Cage Terminals

Figure 12: Overview of spring-cage terminals for connecting the control cables

6.9.2 Connecting the Control Cables of the Sunny Island Inverters

The Sunny Island inverters of the main cluster must be connected to the Multicluster Box via several control cables. These

control cables transmit measurement and control signals between the Sunny Island inverters of the main cluster and the

Multicluster Box.

Cable requirements:

☐ Conductor material: copper
☐ Conductor cross-section: 1.5 mm² to 2.5 mm²

Procedure:

1. Insert the control cables into the Multicluster Box (see Section 9.3.1, page 31).
2. Connect the cables to the spring-cage terminals X106, X112 and X113 (see Section 9.4.2, page 35):

X106: control voltage of the main cluster
X112: control cables from Sunny Island 1 of the main cluster
X113: control cables from Sunny Island 2 of the main cluster

6.9.3 Connecting the BatFuse

Cable requirements:

☐ Conductor material: copper
☐ Conductor cross-section: 1.5 mm² to 2.5 mm²

Position

Designation

Explanation

A

X106

Control voltage of the Sunny Island main cluster

B

X107

DC supply for connection to the BatFuse

C

X110

Connection of control cables from Grid Connect Box or NA Box

D

X111

Connection of control cables from Grid Connect Box or NA Box

E

X112

Connection of control cables to Sunny Island 1 of the main cluster

F

X113

Connection of control cables to Sunny Island 2 of the main cluster