Setting up the level 10r gig e switch, Configuring the gige switch via serial connection – Grass Valley K2 Storage System Instruction Manual v.3.2 Nov.18 2008 User Manual
Page 74

74
K2 Storage System Instruction Manual
July 15, 2008
Chapter 3 Installing the Level 10R Storage System
• Verify that the PC meets system requirements, as specified in
“Control Point PC
system requirements” on page 271
.
• Install the K2 Control Point software.
• Install other supporting software, as specified in
“Control Point PC system
requirements” on page 271
.
• Install and license NetCentral server software. You can install this on the
NetCentral server PC, which can be the K2 configuration Control Point PC. Refer
to the NetCentral User Guide.
“Control point PC description” on page 394
To fix the screen resolution problem seen with NetCentral on the Grass Valley
Control Point PC, do the following:
1. Go to Display properties (right mouse selection of properties on the display area)
2. Select Settings tab
3. Select the Advanced button
4. In the General tab, set the DPI setting to Normal size (96 DPI)
5. Restart the PC
Setting up the Level 10R Gig E switch
These procedures are for the HP ProCurve switch 2900 series. You must use this
switch for iSCSI traffic on Level 10R.
For control and FTP/streaming traffic, it is allowed to use a different brand of switch,
such as a Cisco Catalyst switch, if required by your site. If you are using a non-HP
switch, apply the information in the following procedures accordingly. Refer to the
documentation you received with the switch as necessary.
“Design considerations for Ethernet switches” on page 509
• You need at least two switches, so that the “A” media (iSCSI) network and the “B”
media (iSCSI) network each have their own switch.
• Assign an IP address and logon to each switch. Refer to
switch via serial connection” on page 75
• Set up VLANs on each switch. Refer to
“Configuring the GigE switch via the Web
.
“K2 Ethernet switch description” on page 395
and
considerations for Ethernet switches” on page 509
Configuring the GigE switch via serial connection
NOTE: Make sure you check the switch firmware and upgrade if necessary, as
instructed at the end of this procedure.
The following procedure is for the HP ProCurve switch 2900 series. Do not use this
procedure on other switch models.