Page 23
Commissioning
Commissioning should only be
performed and documented by
specially trained personnel.
When starting up the
complete system, observe
the instructions given in the
manuals for the indoor unit
and outdoor component.
NOTE
Final tasks
■
Re-fit all the dismantled parts.
■
Instruct the operator on how to
use the equipment.
Functional test for
cooling mode
1. Switch on the supply voltage
on.
2. Use the remote control to
switch on the unit and select
the cooling mode, maximum
fan speed and lowest target
temperature.
3. Measure and record all
the required values in the
commissioning report and
check the safety functions.
4. Check the indoor unit
control system using the
functions described in the
chapter "Operation". Timer,
temperature setting, fan speeds
and switching to ventilation or
dehumidifying mode.
Check that the stop valves
and valve caps are tight after
carrying out any work on the
refrigerant circuit. If necessary,
use appropriate sealant
products.
NOTE
5. Check the correct function
of the condensation pipe by
pouring distilled water into the
condensation tray.
A bottle with a spout is
recommended for pouring the
water into the condensation
tray.
23
Unit dimensions
We reserve the right to modify the dimensions and constructional design as part of the ongoing technical development process.
ATY 260 IT / ATY 350 IT
148
567
567
All values in mm
495
470
396
45
25
47