Function test of the cooling and heating modes

1.

Remove the protective caps from the valves.

2.

Start the commissioning procedure by briefly

opening the shut-off valves on the outdoor

unit until the pressure gauge indicates a

pressure of approx. 2 bar.

3.

Check all connections for leaks with leak

detection spray and suitable leak detectors.

4.

If no leaks are found, fully open the shut-off

valves by turning them anti-clockwise using a

spanner. If leaks are found, remedy the faulty

connection. It is imperative that the vacuum

creation and drying steps are repeated.

5.

Activate the main circuit breaker or fuse (to

be provided by the customer).

6.

Use the remote control to switch on the unit

and select the cooling mode, maximum fan

speed and lowest target temperature.

7.

Check the overheating, outside, inside, outlet

and vaporisation temperatures and record

the measured values in the commissioning

report. Check the correct function and set-

tings of all regulation, control and safety

devices.

8.

Check the unit control system using the func-

tions described in the chapter "Operation".

Timer, temperature setting, fan speeds and

switching to ventilation or dehumidification

mode.

9.

Check the correct function of the condensate

drainage line by pouring distilled water into

the condensate tray. A bottle with a spout is

recommended for pouring the water into the

condensate tray.

10.

Switch the indoor unit to heating mode.

11.

During the test run, check the functionality of

all of the previously described safety devices.

12.

Record the measured values into the com-

missioning report and familiarise the operator

with the system.

13.

Remove the pressure gauge. Check that

seals have been fitted in the sealing caps.

14.

Re-install all disassembled parts.