Start-up checklist pre start-up – Greenheck ERCH (476054) User Manual
Page 30

General Description - NOT model specific
Model ERCH Energy Recovery Ventilator
®
30
Line Voltage. Check at unit disconnect.
L1-L2
Volts
L2-L3
Volts
L1-L3
Volts
Motor Amp Draw
Supply Motor Amps
L1
Amps
L2
Amps
L3
Amps
Exhaust Motor Amps
L1
Amps
L2
Amps
L3
Amps
Fan RPM
Correct fan rotation direction?
Supply Fan
RPM
Supply Fan
Yes / No
Measured Airflow
CFM
Exhaust Fan
RPM
Exhaust Fan
Yes / No
Measured Airflow
CFM
Energy Wheel Motor
L1
Amps
L2
Amps
L3
Amps
Every installation requires a comprehensive start-up
to ensure proper operation of the unit. As part of that
process, the following checklist must be completed and
information recorded. Starting up the unit in accordance
with this checklist will not only ensure proper operation,
but will also provide valuable information to personnel
performing future maintenance. Should an issue arise
which requires factory assistance, this completed
document will allow unit experts to provide quicker
resolve. Qualified personnel should perform start-up to
ensure safe and proper practices are followed.
Unit Model No. __________________________________
Unit Serial No. ____________________________________
Heat Pump Model No. ____________________________
Energy Wheel Serial Number _______________________
Compressor 1 Model No. _________________________
Compressor 2 Model No. _________________________
Start-Up Date ____________________________________
Start-Up Personnel Name _________________________
Start-Up Company ________________________________
Phone Number ___________________________________
Pre Start-Up Checklist
Disconnect and lock-out all power switches.
Remove any foreign objects that are located in the
energy recovery unit.
Check all fasteners, set-screws, and locking collars
on the fans, bearings, drives, motor bases and
accessories for tightness.
Check fan rotation.
Rotate the fan wheels and energy recovery wheels
by hand and ensure no parts are rubbing.
Check the fan belt drives for proper alignment and
tension.
Filters can load up with dirt during building
construction. Replace any dirty pleated filters and
clean the aluminum mesh filters in the intake hood.
Verify that non-motorized dampers open and close
properly.
Check the tightness of all electrical wiring
connections.
Verify control wire gauge.
Verify diameter seal settings on the energy recovery
wheel.
Verify proper drain trap installation.
Check condensing fans for any damage or
misalignment. Spin the blades and make sure they
don’t contact any parts and are free-turning without
any resistance.
Look over the piping system. Inspect for oil at all
tubing connections. Oil typically highlights a leak in
the system.
Inspect all coils within the unit. Fins may get
damaged in transit or during construction. Carefully
straighten fins with a fin comb.
If there is an indirect gas-fired furnace in this unit,
refer to the manual provided with this unit for Pre-
Start-Up information.
This unit contains a crankcase heater for each
compressor which needs power supplied to it
24 hours prior to start-up. If start-up is scheduled
in 24 hours, unlock the disconnect power and
energize unit.
Start-Up Checklist
Pre Start-Up