Testing and operation – Gasboy 552A Series User Manual

Page 19

background image

03/07/03

4-1

Section 4

TESTING AND OPERATION



TESTING THE INSTALLATION


Before placing the pump into full operation, you should first test the installation.

1. Place a small quantity of product in storage tank, but do not cover tank or pipe line

connections until pump is operated several times to make certain the system is fully primed
with product.


2.

Operate pump several times, following instructions below, until gasoline is discharged from
hose nozzle. This will fill suction line and pump with gasoline.


3.

Make a final inspection of all pipe lines to insure that connections are absolutely tight.


NOTE: If necessary for more than one pump to be connected to a single outlet from storage tank,

it is imperative that high grade check valves be used in each line to pumps, and must be
placed as close as possible to the connection into main supply line from tank. This is to
prevent a partial vacuum being created in suction lines, causing pumps to operate in a
pulsating manner.


OPERATING INSTRUCTIONS


1.

Reset register assembly to zero by turning instrument knob (located on left side panel) in a
counterclockwise direction.


CAUTION: On units equipped with a built-in interlock, failure to reset register before

attempting to turn dispenser on may result in damage to reset mechanism.


2.

Remove nozzle from nozzle hook.


3. Pull out switch rod and knob assembly (on right side panel). This will turn on motor and

activate the pump.


4. Place nozzle into receiving vehicle and dispense desired quantity of product into vehicle.

NOTE: Nozzle must be manually held open at all times.


5.

Upon completion of delivery, push switch rod and knob assembly in. This will turn the motor
and pump off.


6.

Replace nozzle on nozzle hook.