Flowserve VTP Wet Pit User Manual
Page 11

VERTICAL TURBINE PUMPS (VTPS) CENTRIFUGAL PUMPS ENGLISH 71569224
– 10-13
Page 11 of 76
flowserve.com
Two point lifting of fabricated discharge
2.3.3.1
head types TF, UF & HFH (with or
without pump attached)
Fabricated heads with discharge size mm (in.)
100-200
(4-8)
250-600
(10-24)
700-900
(28-36)
Pin
Dia.
32 (1.25)
38 (1.50)
44 (1.75)
Weight
<2300 (5000)
<4500 (10000)
<6800 (15000)
Three point lifting of fabricated
2.3.3.2
discharge head of type HFL (with or
without pump attached)
HFL STYLE FABRICATED
WITH 3 POINT LIFTING
Lifting of bowl assembly only
2.3.4
Clamp the bowl assembly and center the lifting hook
for lifting and lowering the assembly into the
sump/suction barrel.
a) Lower the bowl assembly until the clamp
extensions rest on the foundation (use
appropriate supports).
b) Build the very first section of the column piping,
and lower the entire assembly to assemble the
next column section.
c) Continue to build until it is ready for discharge
head assembly.
d) Install the discharge head.
e) Assemble the motor.
Example: Lifting of bowl assembly
50 mm (2in.) HOLE
FABRICATED WITH
2 POINT LIFTING
"L"