Operation

Sorensen SLM-1 Chassis

3.2

POWER CONNECTION

Before connecting AC power to the SLM-1 chassis, make sure the power source
matches the power requirements of the SLM-1 electronic load chassis (as marked on
the rear panel) per Section 2.1.1. The power switch in the lower left-of-center area of
the SLM-1 chassis, turns power On/Off to the chassis and to the installed electronic
load module.

PREVENT DAMAGE TO THE LOAD:

Do NOT apply voltage or current

with power switched OFF. Turn ON the power switch to the load PRIOR to
applying voltage or current to the input terminals (i.e., before turning on the
power supply under test).

3.2.1 Power-On

Status

Local/Manual Operation Displays

STORE/RECALL: All LEDs are OFF; BANK LED display shows 01; SL-series
electronic load is in Power On initial state (please refer to the appropriate SL-
series Electronic Load Operations Manual for the startup state of each module).

GPIB Address Setting

1. Press STATE 4+STATE 5 (keys running vertically on left side of chassis)

simultaneously to set the GPIB address.

2. Press UP or DOWN on the BANK keys (lower left corner of chassis) to select

the address number (0-31) (see LED to right of BANK keys).

3. Press STATE 2 to exit GPIB address setting mode.

Figure 3-2 SLM-1 Front Panel Keys and LEDs

3-2