Preparing for operation, 2 connection, 6commissioning – Pilz PNOZ ml2p safe link PDP User Manual
Page 20: 2 preparing for operation, Supply voltage, Connection to a decentralised input module pdp67
6.2
Preparing for operation
6
Commissioning
Pilz GmbH & Co. KG, Felix-Wankel-Straße 2, 73760 Ostfildern, Germany
Telephone: +49 711 3409-0, Telefax: +49 711 3409-133, E-Mail: [email protected]
6-2
6.2
Preparing for operation
6200
Preparing for operation
6-
6.2.1
Download modified project to the PNOZmulti safety system
Download modified project to the PNOZmulti safety system
6-
Verdrahtung_multi_Modul_Betr_geaend_Projekt_BA
As soon as an additional expansion module has been connected to the
system, the project must be amended using the PNOZmulti Configura-
tor. Proceed as described in the operating instructions for the base unit.
6.2.2
Connection
Connection
6-
Betriebsbereitschaft herstellen Anschluss_PNOZ ml2p
`
Supply voltage
`
Connection to a decentralised input module PDP67
Betriebsbereitschaft herstellen Anschluss - LC-Kabel_PNOZ ml2p
`
Connection when using the PSS SB BUSCABLE LC in conjunction with a Pilz self-assembly "PSS67 M12
connector" (see order reference in the Technical Catalogue)
NOTICE
For the commissioning and after every program change, you
must check whether the safety devices are functioning correctly.
Supply voltage
AC
DC
24V
+ 24 V DC
0 V
24V
0V
0V
CAN+
CAN-
VCC
GND
Shield
VCC
CAN-
GND
CAN+
Shield
PNOZ ml2p
PDP67 F 8DI ION
1
2
3
4
5
CAN+
CAN-
VCC
GND
Shield
PNOZ ml2p
PDP67 F 8DI ION
1
2
3
4
5
red
brown
white
green
VCC
CAN-
GND
CAN+
Shield