Installing vertical units, Mounting vertical units, Duct system – WaterFurnace Envision (XL) User Manual
Page 10: Condensate drain
ENVISION 7-25 TONS INSTALLATION MANUAL
11
Control Box
Condensate
Drain
Water Supply
and Return
Connections
Flexible duct
Collar
ACCESS
PA
NE
L
ACCESS
PA
NEL
PAN
EL
AC
CES
S
Figure 6: Typical Vertical Application
Installing Vertical Units
Mounting Vertical Units
Units are available with top/side discharge, left-hand or right-hand return air configurations. Vertical units are assembled on
rails which facilitate moving and placement of the units. It is not necessary to anchor the unit to the floor.
Duct System
A supply air duct flange is provided for field installation to facilitate the secure duct connection at the job site. A flexible
connector is recommended for discharge and return air duct connections on metal duct systems to prevent vibration
transmission. It is recommended that all ductwork be insulated with a minimum of 1/2-inch coated insulation. Installation of
the units with uninsulated ductwork in an unconditioned space is not recommended, as the system’s performance will be
adversely affected.
Condensate Drain
In vertical units, the internal condensate drain assembly consists of a flexible drain tube which is attached to the drain pan
and a 3/4-inch (7-10 tons) and 1-inch (13-25 tons) female pipe thread. An external water trap is not required as the drain
tube serves as a trapping loop. The field-installed piping and unit connection must be properly installed and sealed to
prevent water leakage.