New construction installation — standard grille – Velodyne SC-IWBB User Manual
Page 10

www.velodyne.com
4 -SC-IW Installation Manual
NEW CONSTrUCTION INSTALLATION —
STANdArd GrILLE
Note: This installation process assumes that the installer has access to the open framed 2x4 studded wall with
16 inch spacing. In the event that the stud spacing is larger, an additional 2x4 or other spacer can be used to
fill the space between the SC-IW back box and theneighboring stud.
Step 1 - Install Mudring
Unpack the first carton (SC-IWBB) and place the contents on the floor. Remove the mudring from the packaging.
At this time the decision needs to be made about which direction the woofer will fire (up or down) and therefore
where the grille will be located on the wall. Typically the woofer will fire downwards and the grille will be located
near the floor. (Remember to consider baseboards and other trim work that might be used on the house in this
case.) Once you have decided where to place the grille, staple the mudring to the studs as shown in figure 1.
Figure 1: Install Mudring - The back box is used for reference position only — it is installed in the next step.
Align mud ring to
line on the back box.