15 Replacement of Parts

15.1 General

IMPORTANT:

The replacement parts described in sections

15.5 to 15.9 and section 15.12, will require the removal of the

burner module assembly and the replacement of the burner

door seal and self locking nuts.
Replacement parts that have associated components that

need replacing on removal, i.e. ‘O’ ring, seals, gasket, etc.,

will be supplied and should be fitted.
Replacement of parts must be carried out by a

competent

person approved at the time by the Health and Safety

Executive.
Before replacing any parts of the boiler it should be isolated

from the mains electric supply and the gas should be turned

off at the gas service isolation valve on the boiler, see

diagram 12.1.
Unless stated otherwise parts are replaced in the reverse

order to removal.
After replacing any parts always test for gas tightness and if

necessary carry out functional test of the controls.

Boiler Access

For replacement of parts the front casing and the inner casing

panel of the boiler will need to be removed. To remove undo

the two screws on the underside of the front casing and lift off.

Undo the two screws on the front of the inner front panel and

lift off.
The side panels can be hinged sideways and removed to aid

replacement of parts.
To hinge a side panel undo and remove the three screws

securing each side panel to the boiler, two at the front and

one at the top.

Draining of Boiler Heating Circuit

Drain down the Heating Circuit of the boiler only, by closing

the heating flow and return isolating valves, see diagram 12.2.
Attach a length of hose to the drain point and open the drain

valve, see diagram 12.1.
After servicing or replacing parts, close the drain valve and

remove the hose. Open the heating flow and return isolating

valves and refill, vent and pressurise the heating circuit. See

section 12.1.
Check for leaks.

15.2 Spark Electrode

For access, refer to section 15.1.
Refer to section 13.2 for removal.

15.3 Igniter Unit

For access, refer to section 15.1.
Remove ignition lead and electrical connections then remove

igniter unit by removing two securing screws, see diagram

15.1.

15.4 Ignition Lead

For access, refer to section 15.1.
Pull the spark plug style connector off the spark electrode,

refer to diagram 13.5 and the spade connector connected to

the igniter unit, see diagram 15.1.

Diagram 15.1