beautypg.com

11 electrical connection, 12 commissioning, 2 system controls 24v – Glow-worm Ultracom sxi User Manual

Page 36: 3 mains voltage system controls, 4 electrical cartridge securing, 5 electrical connections - testing, 1 preliminaries - all systems, 2 filling the heating circuit

background image

36

11 Electrical Connection

Diagram 11.4

13488

11.2 System Controls 24V

WARNING: UNDER NO CIRCUMSTANCES MUST

ANY MAINS VOLTAGE BE APPLIED TO ANY OF THE

TERMINALS ON THE 24V CONNECTION PLUG.
Connect the mains supply and system heating controls e.g.

room thermostat as diagram 11.2. External controls should be

fitted in accordance with the rules in force.

11.3 Mains Voltage System Controls

WARNING: UNDER NO CIRCUMSTANCES MUST

ANY MAINS VOLTAGE BE APPLIED TO ANY OF THE

TERMINALS ON THE 24V CONNECTION PLUG.
Connect mains supply and system controls as diagram 11.3.
External controls should be fitted in accordance with the rules

in force.

11.4 Electrical Cartridge Securing

Fit electrical cartridge into the interface housing on completion

of the wiring, see diagram 11.4.
Secure with the two cartridge retaining screws provided in the

cartridge body.

11.5 Electrical Connections - Testing

Carry out preliminary electrical system checks as below:
1. Test insulation resistance to earth of mains cables.
2. Test the earth continuity and short circuit of cables.
3. Test the polarity of the mains.
NOTE: If you require to test the appliance refer to section 14.

IMPORTANT: At the time of commissioning, complete all

relevant sections of the Benchmark Checklist located in the

centre pages of this document.

12.1 Preliminaries - All Systems

The commissioning should be carried out by a

competent

person approved at the time by the Health and Safety

Executive and in accordance with the current issue of

BS6798.
DO NOT operate the boiler without water.
Make sure that the system has been thoroughly flushed

out with cold water and that all cleanser, if used, has been

removed.
Isolate the boiler from the mains electrical supply.
Test for gas tightness and purge air from the gas supply.
IMPORTANT: Before starting the boiler check that all flue

connections are secure and sealed correctly.

12 Commissioning

12.2 Filling the Heating Circuit

With the gas isolation valve closed and with no demand from

any external controls switch on the power supply to the boiler.
The boiler should be in “OFF” mode, this will be indicated

on the user interface display, refer to diagram 12.2. If not,

press the “Mode” button repeatedly until the “OFF” symbol is

displayed, then continue as follows:
1. Open the Central Heating Flow and Return isolating

valves marked ‘A’ using a screwdriver or a 4mm allen

key - slot in line with the axis of the valve (shown closed

in diagram).
2. Fill the heating system to a pressure of 1.0bar. The

system pressure will be displayed on the user interface.

3. Vent all air from the system - repeat as necessary

until the system is full and all the air has been vented.