Dynamic Braking Kits for FlexPak 3000 and WebPak 3000 Digital DC Drives
13
If you are using DB with a Motor Series Field, S1 connected to A2/S1
without an Inverting Fault Circuit
Breaker:
Step 1. Follow the wiring diagram in figure 9 to connect the motor armature and the Dynamic Braking (DB)
Resistor assembly to the FlexPak 3000 drive.
Step 2. Remove the Removable Link (see figure 6). It is a bus section below the A2/S1 terminal and is
accessed through the top of the drive as shown. At the top, the A2/S1 terminal and Removable Link
are fastened with two nuts and bolts, spaced horizontally. Remove them and set them aside along
with the A2/S1 terminal for subsequent re-installation. At the bottom, remove the two bolts spaced
vertically and likewise set them aside. Take the Removable Link (bus section) out of the drive.
Step 3. Replace the lower two vertically-spaced bolts and tighten to 23 Nm (200 in-lb).
Step 4. Replace the A2/S1 terminal fastening it with the upper two horizontally-spaced nuts and bolts
previously removed. Tighten to 23 Nm (200 in-lb).
Step 5. Route the resistor assembly harness as required. Use M10 x 25 mm screws, nuts and washers to
attach resistor assembly harness to DBR and A2/S1 connections on the drive. See figure 9.
Step 6. Connect the S2 terminal to Motor S1 terminal; see the dashed-line in figure 9. Ignore the Inverting
Fault Circuit Breaker illustrated in this figure.
Step 7. Route the wire (cable) and attach to the connections A2/S1 and Motor A2 as shown.
Step 8. Similarly, as shown, route the customer-supplied wire (cable) and attach to the connections A2/S1
and the Motor S1 terminal.
Step 9. Connect the Series Field between the terminals Motor S1 and Motor S2.
Step 10. Follow the wiring diagram in figure 5 to verify that the jumper across terminals 3 and 4 on the FIELD/
DB terminal block is installed. Follow the wiring diagram in figure 5 to install the jumper across
terminals 3 and 4 on the FIELD/DB terminal block.
Step 11. Remove the lockout and tag from the power to the drive.
Step 12. Turn on power to the drive.