Step 5
Cut and terminate
For perimeter cuts, cut in and terminate cross tees at both ends of the vault.
cross tees for
1.
If the vault terminates at a perpendicular wall, attach a complete main-tee rib against the wall using wall
perimeter cuts
attachment clips
(Figure 19)
. Space the clips about 4 on center (every sixth slot). Use the ledge of this rib to
attach cross tees. Cut cross tees to fit and permanently attach them using self-drilling screws.
2.
If the barrel vault terminates at a half dome, cut cross tees to fit and mechanically fasten the cut ends to the
face of the dome spokes.
Figure 19 – Insert clip
Step 6
Finish the vault
Apply S
heetroCk
®
brand gypsum panels to the exposed surface of the suspension system as indicated on the
architectural plans. Check the architectural plans for any additional perimeter transition treatments that may be
required. Examples may be found in the USG drywall suspension system brochure (AC12).
A
1) insert tab through tee slot
B
2) fold against tee web
) screw-attach to wall
Technical Service 800 USG.4YOU
Samples, Literature 888 874.2450
Customer Service 800 950.3839