2 stationary pumping operations, Pumping from a hydrant, general operation, Figure 3-1: driver’s compartment indicator lights – Hale RSD User Manual
Page 28: Stationary pumping operations
❑ Operation
28
Section 3: Operating
Hale Products, Inc., Nov.2005, Rev-A
3.2
STATIONARY PUMPING OPERATIONS
Pumping From a Hydrant, General Operation
1.
Position the truck for the best hydrant hookup and discharge hose layout.
2.
Bring the truck to a complete stop and apply the truck parking brake.
3.
Shift the truck transmission to the NEUTRAL position. See WARNING !
note on page 27.
4.
Make sure the truck is at a complete stop before you attempt to shift from
ROAD to PUMP. Also see heading “Pump-To-Road Shift Procedures” on
page 39.
Engage the PTO (power take-off) per the PTO manufacturer’s instructions
(move the in-cab pump shift control valve from the ROAD position to the
PUMP position). The GREEN shift warning lights illuminate in a second or
two, indicating a complete shift. (See Figure 3-1: “Driver’s Compartment
Indicator Lights.”)
Figure 3-1: Driver’s Compartment Indicator Lights
Note: If the truck manufacturer has used another in-cab valve to achieve pump shift
or offers an electric switch, follow the instructions supplied with that valve.