Unit start-up checklist, I. preliminary information, Iii. start-up – Bryant F User Manual
Page 85
85
UNIT START-UP CHECKLIST
I. PRELIMINARY INFORMATION:
MODEL NO.:
DATE:
______________
SERIAL NO: _____________________________________
TECHNICIAN: ___________________________________
BUILDING LOCATION:____________________________
II. PRE-START-UP (insert check mark in box as each item is completed):
j
VERIFY THAT ALL PACKAGING MATERIALS HAVE BEEN REMOVED FROM UNIT
j
VERIFY THAT CONDENSATE CONNECTION IS INSTALLED PER INSTALLATION INSTRUCTIONS
j
VERIFY THAT FLUE HOOD IS INSTALLED
j
CHECK ALL ELECTRICAL CONNECTIONS AND TERMINALS FOR TIGHTNESS
j
CHECK TO ENSURE NO WIRES ARE TOUCHING REFRIGERANT TUBING OR SHARP EDGES
j
CHECK GAS PIPING FOR LEAKS
j
CHECK THAT RETURN--AIR FILTER IS CLEAN AND IN PLACE
j
VERIFY THAT UNIT INSTALLATION IS LEVEL
j
CHECK FAN WHEEL AND PROPELLER FOR LOCATION IN HOUSING/ORIFICE AND VERIFY SETSCREW IS TIGHT
j
VERIFY PULLEY ALIGNMENT AND BELT TENSION ARE CORRECT
III. START-UP
ELECTRICAL
SUPPLY VOLTAGE
L1-L2
L2-L3
L3-L1
COMPRESSOR 1
L1
L2
L2
COMPRESSOR 2
L1
L2
L2
INDOOR FAN AMPS
L1
L2
L2
TEMPERATURES
OUTDOOR-AIR TEMPERATURE
DB
WB
RETURN-AIR TEMPERATURE
DB
WB
COOLING SUPPLY AIR
DB
WB
GAS HEAT SUPPLY AIR
DB
PRESSURES
GAS INLET PRESSURE
IN. WG
GAS MANIFOLD PRESSURE
IN. WG (LOW FIRE)
IN. WG (HI FIRE)
REFRIGERANT SUCTION
CIR 1
PSIG
TEMP _F
CIR 2
PSIG
TEMP _F
REFRIGERANT DISCHARGE
CIR 1
PSIG
TEMP _F
CIR 2
PSIG
TEMP _F
j
VERIFY REFRIGERANT CHARGE USING CHARGING CHARTS
j
VERIFY THAT 3--PHASE SCROLL COMPRESSORS ARE ROTATING IN CORRECT DIRECTION
580J