beautypg.com

Warning – Howard HI-110 Network Transformer User Manual

Page 23

background image

Document 2.4.128, Revision 2

August, 2012

23

Network Transformer Instruction Manual

1. Insulation Resistance Test. Refer to “Insulation

Resistance Test” for instructions.

2. Turns Ratio Test. Refer to “Ratio Test” for

instructions.

3. Insulation Power Factor Test (This test cannot be

performed on a transformer having a secondary

neutral that is solidly grounded.)

4. Fluid quality tests, such as moisture content,

power factor, dielectric strength and dissolved

gas analysis.

Exterior Paint Finish

Any damage to the exterior paint finish that exposes

the primer coat or bare metal should be repaired

immediately in order to prevent corrosion. Areas to

be repaired should be clean and dry. The surface

should be sanded to remove rust, loose paint

flakes and other debris. The surface should then be

cleaned with a suitable solvent to remove any oil,

grease or other contaminants. At lease two coats

of high-quality touchup paint should be applied to

the damaged area. Touch-up paint is available in

aerosol cans from the Howard Industries Transformer

Division.

Fluid Leaks

Check the tank for indication of fluid leaks, looking

carefully at weld seams and at tank fittings, such as

bushings, gauges, plugs and valves. In addition to

the presence of fluid residue, a low reading on the

fluid level gauge is further indication of a possible

fluid leak. Fluid leaks should be repaired as soon as

possible to prevent moisture contamination of the

insulating fluid and to prevent internal flashover due

to low fluid level.

WARNING

FAILURE TO FOLLOW THE INSTRUCTIONS

BELOW COULD RESULT IN DEATH OR SERIOUS

PERSONAL INJURY AND MAY

ALSO RESULT IN

DAMAGE TO THE EQUIPMENT.
• Do not energize the transformer if the fluid

level is low.

• Maintain proper fluid level while the

transformer is energized.

If a fluid leak is suspected, investigate thoroughly

to determine if an actual leak does exist on the

transformer. False indications of a leak can occur

as a result of residual fluid that was not sufficiently

cleaned during the oil-filling process. In some cases

silicone lubricant used to install high-voltage bushing

inserts can spread to the tank surface, giving a false

indication of a fluid leak.

To verify that a fluid leak exists, clean the suspected

leak area with an appropriate solvent to completely

remove the fluid and observe the area for

reappearance of fluid. Pressurize the tank with dry

air or dry nitrogen through the pressure test fitting

to a pressure of 3-4 PSIG. Let the tank stand under

pressure for one to two hours, then examine the tank

and fittings for leaks. Leaks above the fluid level can

be detected by applying soap solution to all welds,

joints, pipe fittings, and cable connections.

In many cases a small pin-hole tank leak or leak

from a bushing, gauge, valve or other fitting can be

repaired on site. Pin-hole and weld seam leaks can

usually be repaired by welding on a de-energized

transformer.

Bushing leaks can sometimes be corrected by

tightening the bushing clamp bolts. Do not exceed

the recommended torque values listed in Table 4 to

prevent the possibility of bushing or gasket damage.

Audible Sound Level

It is normal for transformers to emit an audible

humming sound, which is primarily caused by

alternating magnetic flux in the transformer core.

Amplitude and harmonic content of the sound is

influenced by transformer size, the energizing voltage

level and sinusoidal purity, load conditions and

acoustic conditions at the installation site. Unusual

sounds should be investigated, as this might indicate

a potential problem.

Refer to NEMA Standards Publication TR-1,

Transformers, Regulators and Reactors, and IEEE

Standard C57.12.90, IEEE Standard Test Code for

Liquid-Immersed Distribution, Power, and Regulating

Transformers, for more information about design

sound levels and factory sound testing.