Identifying rack server shipping carton contents, Installing hardware options, Installing the server into the rack – HP ProLiant DL585 G2 Server User Manual
Page 25: Installing the cable management arm, Powering up and configuring the server
Setup 25
Furthermore, you must be sure that all power distribution devices used in the installation, such as branch
wiring and receptacles, are listed or certified grounding-type devices.
Because of the high ground-leakage currents associated with multiple servers connected to the same
power source, HP recommends the use of a PDU that is either permanently wired to the building’s branch
circuit or includes a nondetachable cord that is wired to an industrial-style plug. NEMA locking-style plugs
or those complying with IEC 60309 are considered suitable for this purpose. Using common power outlet
strips for the server is not recommended.
Identifying rack server shipping carton contents
Unpack the server shipping carton and locate the materials and documentation necessary for installing the
server. All the rack mounting hardware necessary for installing the server into the rack is included with the
rack or the server.
The contents of the server shipping carton include:
•
Server
•
Power cord
•
Hardware documentation, Documentation CD, and software products
•
Rack-mounting hardware
In addition to the supplied items, you may need:
•
Hardware options
•
Operating system or application software
•
PDU
Installing hardware options
Install any hardware options before initializing the server. For options installation information, refer to the
option documentation. For server-specific information, refer to "Hardware options installation (on page
Installing the server into the rack
Refer to the installation instructions that ship with the rack kit to install the server into the rack.
Installing the cable management arm
Refer to the installation instructions that ship with the rack kit to install the cable management arm.
Powering up and configuring the server
To power up the server, press the Power On/Standby button.
During the initial boot, the server configuration automatically defaults to prepare for operating system
installation.