4-3 Starting the Hopper Loader

1. Insert the pickup probe into the material supply.

2. Turn on compressed air to the unit.

3. Plug in power to the control enclosure.

4. Move the power switch on the Series One graphic panel to the

ON position.

4-4 Changing the Conveying Sequence

!

DANGER

DISCONNECT POWER

BEFORE

OPENING THE CONTROL BOX.

Electric current, CAPABLE OF
CAUSING INJURY OR DEATH
, MAY BE
PRESENT in the controller enclosure
during these procedures.

The adjustments listed in this section
must be performed

ONLY

by a qualified,

safety-conscious technician.


The Series One controller is a time-fill mode controller, and has sixteen (16) loading
sequences to select. Make sure you avoid over-filling the hopper! Figures 7 and 8 list
loading times and number of blowback pulses in each sequence. Use the chart as your
model;
select a sequence that suits your needs.