5. Service and maintenance

www.nord.com B2000-GB-0413

-39-

General overhaul

With Category 2G and 2D gear units, a general overhaul is necessary after a specified longer
period of operation. The specification of the operating period in terms of operating hours, after
which a general overhaul must be carried out, can be seen from the rating plate data in field MI.

Alternatively, the maintenance class CM can be used to determine the operating period after
which a general overhaul must be carried out. The data in field MI of the rating plate is then e.g.:
MI CM=5.

The time for the general overhaul with the stated maintenance class CM is calculated as follows:

NA= CM

 fL

 kA

NA: Number of years since commissioning. With calculated values of NA which exceed 10

years, a general overhaul is due 10 years after commissioning.

CM: Maintenance class according to field MI of the rating plate

fL:

Running time factor

fL= 10

Maximum running time 2 hours per day

fL= 6

Running time 2 to 4 hours per day

fL= 3

Running time 4 to 8 hours per day

fL= 1.5 Running time 8 to 16 hours per day

fL= 1

Running time 16 to 24 hours per day

kA: Utilisation

factor

If the utilisation factor is unknown, KA=1.

If the actual power required by the application is known, longer maintenance intervals may
result. The utilisation factor may be calculated as follows:

3

tat

P

1

P

A

k





P1: Max. permissible drive power or motor power in kW according to the rating plate

Ptat: Actual drive power or motor power in kW which is required by the application at the rated

speed. This is determined e.g. by measurements.

With variable loads with differing actual drive powers with rated speeds Ptat1, Ptat2,
Ptat3, … with known percentage times q1, q2, q3, …, the following equivalent average
drive power applies:

3

3

3

3

2

3

2

1

3

1

100

100

100

...

q

P

q

P

q

P

P

tat

tat

tat

tat

Danger!

The general overhaul must be carried out by qualified personnel in a specialist
workshop with appropriate equipment in observance of national regulations and laws.
We urgently recommend that the general overhaul is carried out by NORD Service.