Commissioning – NORD Drivesystems B2000 User Manual
Page 31
4. Commissioning
www.nord.com B2000-GB-0413
-31-
4.5 Checking the gear unit
During a test run under full load, the gear unit should be checked for:
Unusual noises, such as grinding, knocking or rubbing noises
Unusual vibrations, oscillations and movements
Production of steam or smoke
After the test run, the gear unit should be checked for:
Leaks
Slippage of the shrink disks. For this, the cover should be removed and a check carried out
whether the marking described in Section 3.10 shows a relative movement of the hollow shaft
of the gear unit and the machine shaft. Then the cover should be fitted as described in
Section 3.11.
Note!
Shaft sealing rings are rubbing seals and have sealing lips made from an elastomer
material. These sealing lips are lubricated with a special grease at the factory. This
reduces the wear due to their function and ensures a long service life. An oil film in the
region of the rubbing sealing lip is therefore normal and is not due to leakage.
4.6 Checklist
Checklist
Object of the check
Checked on:
Information –
see Section
Is any transportation damage or damage apparent?
Section 3.3
Does the labelling on the rating plate conform to the specifications?
Section 3.4
Does the configuration on the rating plate conform to the actual installation?
Section 0
Is the pressure vent screwed in?
Section 3.6
Do all drive and driven elements have ATEX approval?
Section
Are the external gear shaft forces within permitted limits (chain tension)?
Section
Are contact guards fitted to rotating components?
Section 0
Does the motor also have a relevant ATEX approval?
Section 3.12
Is the temperature sticker affixed?
Section 3.14
Has the correct oil level for the configuration been checked?
Section 4.1
Is the automatic lubricant dispenser activated?
Section 4.2
Has the temperature measurement been carried out?
Section 4.3
Has the centre of the temperature sticker turned black?
Section 4.3
Danger!
The drive must be shut down and Getriebebau Nord consulted if any irregularities are
observed during the checks described above.