Model CX-IR

Initial Operational Tests


After a warm up period of 1 hour (or when zero has stabilized), the sensor should be checked to verify
sensitivity to the target gas.

Material Requirements

• Splash Guard with integral Cal Port and with Wind Guard (Detcon PN 613-120000-700) -or-

• Threaded Calibration Adapter (Detcon PN 943-000006-132) - or -

• Teflon Calibration Adapter for highly reactive gases (Detcon PN 943-01747-T05)

• Detcon Span Gas; 50% of range target gas in balance N2 or Air at fixed flow rate between 200-

500cc/min (500cc/min is preferred)

12. Attach the calibration adapter to the Splashguard Adapter Assembly or connect tubing to integral cal

port. It is recommended that the Wind Guard (Detcon PN 943-000000-000) is installed over the Splash
Guard during calibration.

13. Apply the test gas at a controlled flow rate of 200 - 500cc/min (500cc/min is the recommended flow).

Observe that the ITM display increases to a level near that of the applied calibration gas value.

NOTE

Wind Guard must be used when calibrating with the integral cal port to ensure proper
calibration.

14. Remove test gas and observe that the display decreases to 0.

15. If a calibration adapter was used during these tests, remove it from the unit, and re-install the Splash

Guard.

16. If the wind guard was used, remove the wind guard.


Initial operational tests are complete.

CX-IR Combustible gas sensors are factory calibrated prior to shipment, and should not require significant
adjustment on start up. However, it is recommended that a complete calibration test and adjustment be
performed 16 to 24 hours after power-up. Refer to calibration instructions in Section 3.3.