Onfiguring, Ctions, 5 configuring park actions – LT Security IPPTZ762 User Manual
Page 36
![background image](/manuals/363862/36/background.png)
User Manual of IR Network Speed Dome
35
Figure 5-6 Task Types
(5) After you set the scheduled task, you can copy the task to other days
(Optional).
(6) Click
to save the settings.
The time of each task can’t be overlapped. Up to 10 tasks can be configured for
each day.
5. Click
to save the settings.
5.5 Configuring Park Actions
Purpose:
This feature allows the dome to start a predefined park action (scan, preset, pattern
and etc.) automatically after a period of inactivity (park time).
Scheduled Tasks function is prior to Park Action function. When these two
functions are set at the same time, only the Scheduled Tasks function takes effect.
Steps:
1. Enter the Park Action Settings interface:
Configuration > Advanced Configuration> PTZ > Park Action