1. AGS-system layout
 
The AGS-system contains the following parts: 
1. Control
box;
2. Guide
units;
3. Guide unit cables; 
4. Junction 
box;
5. Zone supply cables.
 
The points 4 and 5 are used when the number of Guide units are higher than the Control 
box itself can control. 
 
The default distance between Guide units is 1 meter. This may be changed depending on 
application. 
 
See picture next page. 
 
For more information see document "Controls overview". 
 
1.1 Integrator responsibility
 
Some parts of installation is application depending and part of the integrator’s 
responsibility: 
1. Box mounting frames; 
2. Wire 
ways;
3. Zone supply conductors (see chapter “4. Zone supply”)