Archived, Specification, Assembly instruction – FlexLink AGS Монтаж User Manual
Page 10: Safety information, Installing the guide rail to the guide units
![background image](/manuals/329529/10/background.png)
Specification
Unit/Dept. Document
type Date
APD/Research & Development
Assembly Instruction
2006-05-19
Issued by
Document number Page
Approved
by
Fredrik Johansson
3928587-03
10/12
FJn
3928587_03.DOC
Archived
5. Safety information
It is important to secure that products on the conveyor can not fall down on personal and
cause personal injury. Fall protection may need to be added below the conveyor. This is
specifically important where conveyors are running overhead a gangway. There is a risk
that the customer runs the system adjusted for the wrong product, this might increase the
risk of falling products. It is the integrators responsibility to install protections.
6. Installing the guide rail to the Guide units
Attach all Guide units to the conveyor. It is very important that the Guide units are parallel
to each other (see picture below). A and B must be equal.
Check that all Guide units are in outer position, this is the way they are delivered. Install
the guide rails adjusted for the widest product.
When the power supply is installed, run the system in and out and check that everything
runs smooth. Built in tensions can stop the system.
If a curve is made of segments placed at the same level it is important that the ends of the
segments never comes in contact with each other (see picture below). Check the whole
stroke of the guide unit!
A
B
A
A>0