4 completing the installation checklist – GE Industrial Solutions SG Series UL LISTED BATTERY CABINETS User Manual
Page 10

Modifications reserved
Page 11/36
Installation and O&M manual for SG battery cabinets - OPM_SGS_XXU_ISG_BAT_XUS_V020.doc
Installation Guide SG Series UL Battery cabinets
4 COMPLETING THE INSTALLATION CHECKLIST
The final step in installing your battery cabinet is to complete the Installation Checklist. This checklist ensures
that you have installed all hardware, cables, and other equipment. Completing all items on the checklist will
ensure a smooth installation. Make a copy of the Installation Checklist before filling it out, and retain the
original. After completing your installation, a GE Service Representative will be able to verify the operation of
your battery cabinet, and commission it to support your critical load. The service representative cannot
perform any installation tasks other than verifying that the battery cabinet has been correctly installed. Service
personnel may request a copy of the completed Installation Checklist to be sure you have completed all
applicable equipment installation requirements.
NOTE
The Installation Checklist MUST be completed prior to starting the UPS system for the first time.