2.0 Unpacking/Inspection/Storage/Disposal

2.1

Unpacking the new UPS equipment 15/25/30 kVA:

Upon receipt of the UPS, a careful inspection for shipping damage should be made. Units

shipped within North America are shrink-wrapped; those outside North America are crated.

1. Remove packing material.

1a. For international units,

remove the screws that

attach the shipping crate

to the pallet.

Remove the crate and

foam

packing material.

TOP HEAVY EQUIPMENT. IMPROPER LIFTING CAN RESULT IN INJURY OR
DEATH. LIFT AND MOVE CAREFULLY AND ONLY WITH ADEQUATE
EQUIPMENT AND TRAINED PERSONNEL. THIS EQUIPMENT WILL TIP OVER
EASILY UNTIL FIXED IN PLACE.

DANGER

2. Unbolt the rails from both the unit

and the shipping pallet.

Place the rails on the front of

the

pallet.

Use the four 1/2 x 3" bolts to

secure the rails to the shipping

pallet.

Attach the rails as shown in the

front to the front of the pallet.

3. Place the tie brackets in the slots at

the lower end of the ramps.
SLOWLY roll the unit down the
ramp.