To connect a FortiGate-5140 PEM to data center DC power

1 Attach the ESD wrist strap to your wrist and to an ESD socket or to a bare metal

surface on the chassis or frame.

2 Loosen the screws and remove the terminal block cover from the FortiGate-5140 PEM.
3 Connect the DC power wires (see

Figure 9

):

• Connect a black -48V power wire from the data center DC power source to

connector 1 on the FortiGate-5140 PEM terminal strip labeled -48V/-60 VDC nom.

• Connect a black -48V power wire from the data center DC power source to

connector 2 on the FortiGate-5140 PEM terminal strip labeled -48V/-60 VDC nom.

• Connect a black -48V power wire from the data center DC power source to

connector 3 on the FortiGate-5140 PEM terminal strip labeled -48V/-60 VDC nom.

• Connect a black -48V power wire from the data center DC power source to

connector 4 on the FortiGate-5140 PEM terminal strip labeled -48V/-60 VDC nom.

• Connect a red RTN return wire from data center RTN to connector 1 on the

FortiGate-5140 PEM terminal strip labeled RTN.

• Connect a red RTN return wire from data center RTN to connector 2 on the

FortiGate-5140 PEM terminal strip labeled RTN.

• Connect a red RTN return wire from data center RTN to connector 3 on the

FortiGate-5140 PEM terminal strip labeled RTN.

• Connect a red RTN return wire from data center RTN to connector 4 on the

FortiGate-5140 PEM terminal strip labeled RTN.

4 Secure the power cabling to the chassis using tie wraps and the back cable tray.
5 If required, label the black wires -48V.
6 If required, label the red wires RTN.
7 Re-attach the terminal block cover to the FortiGate-5140 PEM.

Connecting the FortiGate-5140 chassis to data center ground

The FortiGate-5140 chassis includes a ground terminal on the lower left side of the
FortiGate-5140 back panel (see

Figure 2 on page 7

). The shelf ground terminal provides

two M6 bolts to connect a double-lug ground terminal cable. This connector must be
connected to data center ground.
You need the following tools and equipment to connect the FortiGate-5140 chassis to
ground:
• A number 2 Phillips screwdriver.
• An electrostatic discharge (ESD) preventive wrist or ankle strap with connection cord.
• One green AWG-6 stranded wire with terminal lug with 45° angle tongue attached.