F. install firestops – Heat & Glo Fireplace 2197-980 User Manual
Page 41

41
Heat & Glo • SOHO-N-AUB • 2197-980 Rev. G • 2/13
10 in. (254 mm)
10 in. (254 mm)
INTERIOR
WALL SHIELD
F. Install Firestops
For Horizontal Runs - Firestops are REQUIRED on both
sides of a combustible wall through which the flue passes.
To install firestops (heat shield) for horizontal runs that pass
through either interior or exterior walls:
• Cut a 1 in. x 1 in. (25 mm x 25 mm) hole through the wall.
• Position the firestops on both sides of the hole previously
cut and secure the firestops with nails or screws.
• The pipe opening of the firestops
MUST BE placed
towards the bottom of the firestop.
• Continue the flue run through the firestop.
Figure 10.10 Flue Pipe & Firestop
CEILING
NEW
FRAMING
MEMBERS
EXISTING CEILING
JOISTS
CHIMNEY
HOLE
A
B
Figure 10.11 Hole and New Framing Members
For Vertical Runs - One firestop is REQUIRED at the hole
in each ceiling through which the flue passes.
To install firestops for vertical runs that pass through
ceilings:
• Position a plumb bob directly over the center of the
vertical flue component.
• Mark the ceiling to establish the centerpoint of the flue.
• Drill a hole or drive a nail through this center point.
• Check the floor above for any obstructions, such as
wiring or plumbing runs.
• Reposition the fireplace and flue system, if necessary,
to accommodate the ceiling joists and/or obstructions.
• Cut a 9 in. x 9 in. (229 mm x 229 mm) hole through the
ceiling when using SLP pipe. Use the firestop pipe open-
ing as a guide.
• Frame the hole with framing lumber the same size as
the ceiling joists.
A
B
SLP
9 in. (229 mm)
9 in. (229 mm)
Figure 10.12 Ceiling Firestop (Ceiling Side)
Figure 10.13 Attic Firestop
CEILING
CEILING FIRESTOP
RAFTER
NAILS (4 REQUIRED)
JOIST
CEILING FIRESTOP
CEILING
NAILS (4 REQUIRED)
If the area above the ceiling
IS an attic, position and secure
the firestop on top of the previously framed hole.
If the area above the ceiling is
NOT an attic, position
and secure the ceiling firestop on the ceiling side of the
previously cut and framed hole.