For Vertical Terminations - To locate the vent and

install the vent sections:
• Locate and mark the vent centerpoint on the under-

side of the roof, and drive a nail through the

centerpoint.

• Make the outline of the roof hole around the

centerpoint nail.

• The size of the roof hole framing dimensions

depend on the pitch of the roof. There MUST BE a

1-inch (25.4 mm) clearance from the vertical vent

pipe to combustible materials.

• Mark the roof hole accordingly.
• Cover the opening of the installed vent pipes.
• Cut and frame the roof hole.
• Use framing lumber the same size as the roof

rafters and install the frame securely. Flashing

anchored to the frame must withstand heavy winds.

• Continue to install concentric vent sections up

through the roof hole (for inside vent installations) or

up past the roof line until you reach the appropriate

distance above the roof (for outside terminations).

WARNING:

MAJOR U.S. BUILDING CODES SPECI-

FY MINIMUM CHIMNEY AND/OR VENT

HEIGHT ABOVE THE ROOF TOP. THESE

MINIMUM HEIGHTS ARE NECESSARY IN

THE INTEREST OF SAFETY. SEE THE

FOLLOWING DIAGRAM FOR MINIMUM

HEIGHTS, PROVIDED THE TERMINA-

TION CAP IS AT LEAST TWO (2) FEET

FROM A VERTICAL WALL AND 2-FEET

BELOW A HORIZONTAL OVERHANG.

NOTE

This also pertains to vertical vent systems installed

on the outside of the building.