2. To set a new NetID, set the rotary switch C to the
determined NetID using a flat-blade screwdriver
(blade width: 2.5 mm).
3. To deactivate communication via BLUETOOTH,
set the rotary switch C to position 0 using a flat-
blade screwdriver (blade width: 2.5 mm). This
will protect your PV system from unauthorized
access.
☑ The inverter will adopt the setting after commissioning. This can take up to five minutes.
7.4
Commissioning the Inverter
Requirements:
☐ The inverter must be correctly mounted.
☐ The circuit breaker must be correctly rated and mounted.
☐ All cables must be completely and correctly connected.
☐ Unused DC inputs must be sealed using the corresponding DC connectors and sealing plugs.
☐ The country data set must be set correctly for the country or the purpose.
Procedure:
1. Insert the lower enclosure lid from above and
fold it down. The screws must protrude from the
lower enclosure lid.
7 Commissioning
SMA Solar Technology AG
Operating Manual
37