beautypg.com

4 commissioning the inverter, Commissioning the inverter – SMA STP 15000TL User Manual

Page 37

background image

2. To set a new NetID, set the rotary switch C to the

determined NetID using a flat-blade screwdriver
(blade width: 2.5 mm).

3. To deactivate communication via BLUETOOTH,

set the rotary switch C to position 0 using a flat-
blade screwdriver (blade width: 2.5 mm). This
will protect your PV system from unauthorized
access.

☑ The inverter will adopt the setting after commissioning. This can take up to five minutes.

7.4

Commissioning the Inverter

Requirements:

☐ The inverter must be correctly mounted.
☐ The circuit breaker must be correctly rated and mounted.
☐ All cables must be completely and correctly connected.
☐ Unused DC inputs must be sealed using the corresponding DC connectors and sealing plugs.
☐ The country data set must be set correctly for the country or the purpose.

Procedure:

1. Insert the lower enclosure lid from above and

fold it down. The screws must protrude from the
lower enclosure lid.

7 Commissioning

SMA Solar Technology AG

Operating Manual

37

STP15-17TL-10-BE-en-10

This manual is related to the following products: