beautypg.com

Secondary installation – Enviro Haven Direct Vent Fireplace User Manual

Page 31

background image

31

Figure 48. Install Fan Control

Box.

Figure 49. Install Fan Control Nut.

Secondary Installation

6. Re-install the screws for the back cover and the stand-off.
7. Remove the two (2) screws holding the control panel in place. Pull the panel out of the way.
8. Slide the snap switch in place under the holding tabs above the SIT valve (see Figure 47).
9. Remove knob and nut from the fan controller. Place the dial stud through the fan hole in the control

board through the back to the front (see Figure 48). Tighten the nut on the front side to keep the fan

controls in place (see Figure 49), then install the knob onto the stud.

10. Use marrettes to connect the fan wiring harness wires to the house wiring when the Haven is

installed.

11. Re-install the control panel.

Figure 45: Move Back Stand-

Off.

Figure 46: Installing Fan

Through the Back.

Figure 47: Installing Temperature

Sensor.

O

PTIONAL

F

AN

K

IT

I

NSTALLATION

T

HROUGH

F

RONT

OF

H

AVEN

:

1. Ensure the appliance is turned off and cool.
2. Remove the fascia, glass door (see M

AINTENANCE

A

ND

S

ERVICE

- G

LASS

D

OOR

R

EMOVAL

), logset, embers

and firebox liner.

3. Remove the two (2) screws holding the control panel in place. Pull the panel out of the way.

Figure 50. Remove the pilot shield, orifice and valve assembly.

4. To remove the burner undo

the wing nut under the right

side of the burner (see Figure

8) and remove the screw. Lift

the right end of the burner

up, slide it to the left (off of

the main orifice), then up and

out.

5. Remove the pilot shield,

orifice and valve assembly

(see Figures 50).