beautypg.com

4 positioning of the electric cables, Remko pump groups hgm / hgu – REMKO HGM-HGU User Manual

Page 16

background image

2

4.

Insert the insulation (3) by pushing down the

top side of the rear insulation half-shell (2).

2

3

5.

Continue as described in point (9) for wall

installation.

6.

Open the ball valve of the return flow again.

7.

Install the electric cables (see: positioning of

the cables section).

8.

Close the pump group using the front part of

the insulation (1).

2

1

4.4

Positioning of the electric

cables

The electric cables must be installed by qualified

personnel, in order to avoid endangering people's

safety and material damage. The insulation half-

shells were developed in such a way to ensure the

greatest degree of flexibility possible with regard to

cable arrangement in the insulation. There are

appropriate recesses for cable harnesses and

these enable side access to the insulation (2).

2

REMKO PUMP GROUPS HGM / HGU

16