3 installation on the distributor, Installation on the distributor – REMKO HGM-HGU User Manual
Page 15

13.
Close the pump group using the insulation
half-shell (1).
1
4.3
Installation on the distributor
The pump groups can be installed on distributors
with an integrated hydraulic compensator, on
standard distributors with a separate hydraulic
compensator and on series distributors. For
optimum installation, the nozzles of the distributor
should be at least 60mm away from the wall.
1.
First carry out installation steps 1-4 for wall
installation.
2.
To aid installation, start the installation in the
middle of the distributor and then continue
with the outer connections; install the inlet (4)
and the return flow (5) on the distributor
using the screw connection enclosed in the
packaging or using the required connecting
pieces (flat-sealing connections are recom-
mended).
4
5
3.
Insert the insulation half-shell (2); if the dis-
tributor is installed too close to the wall, you
must insert the rear side (2) of the two insula-
tion half-shells before you install the inlet and
the return flow (4 and 5).
15