Online power – OnLine Power Phase Stabilizer User Manual
Page 66
OnLine Power
6002-032 REV H
4-3
4-2-1
Installation for REPO (continued)
4.
Connect 2 wires in REPO cable to terminals on REPO switch as shown in Illustration 4-2.
5.
Turn OFF main facility circuit breaker, lock and tagout in accordance with OSHA requirements.
6.
Open front door of Power Conditioner.
7. Set
IMCB
to
OFF.
8.
Remove floor tiles as required to route REPO cable from REPO box to Power Conditioner.
9.
Route REPO cable up through opening in floor (as applicable) and into conduit entry opening.
10. Locate the two-terminal REPO terminal block in the Power Conditioner.
11. Connect the 2 wires in REPO cable to REPO terminal block. See Illustration 4-2.
12. Replace floor tiles as required.
13. Set
IMCB
to
ON.
14. Close front door of Power Conditioner.
15. Set main facility circuit breaker to ON.
REPO SWITCH
TB5
TO T.B.
N.O.
+28 VDC
SHUNT TRIP
3
4
REPO WIRING
ILLUSTRATION 4-2