Greenheck MSX (470658) User Manual
Page 7

7
Modular Supply Make-Up Air Unit
®
Installation of Evaporative Cooling
Module (optional)
NOTE
Small evaporative coolers ship attached to the base
unit and require no additional mounting.
NOTE
The use of all lifting lugs and a set of spreader bars is
mandatory when lifting the evaporative cooling module.
NOTE
When mounting the evaporative cooler, it is important
that it is level to ensure proper operation and water
drainage.
Metal Cover
Equipment
Support
Equipment Support
Placing Evaporative Module
Securing Evaporative Module
1. Locate Equipment Support(s). Position equipment
support(s) on the roof (reference the CAPS submittal
for placement of equipment support(s) in relation
to the unit).
Verify that all
unit supports
are level, shim
if necessary.
Attach
equipment
support to the
roof, remove
metal cover,
flash to wooden
nailer and reinstall cover.
4. Secure Cooling Module to Unit. Use self-tapping
screws to fasten the cooling module to the base
unit along the top and down both sides. Fasten at
the top through the flanges. To fasten the sides,
the media must be removed. To remove the media,
first remove the access panel on the evaporative
module and disconnect the evaporative pump(s). The
media will now slide out. With the media removed,
you can access the side fastening points inside the
evaporative module. With all the screws in place,
reinstall the media, reconnect the pumps and reinstall
the access panel.
Sealant
3. Set Evaporative Cooling Module. Use a crane
and a set of spreader bars hooked to the factory lifting
lugs to lift and center the module on the equipment
support(s). The flange on the evaporative cooler should
overlap the flange on the unit.
2. Apply Sealant. Apply an appropriate sealant around
the airstream opening to create an air tight seal.