Installation evaporative cooler piping (optional), Install the water supply line, Install the drain line – Greenheck DG/DGX Pilot Ignition (470651_IOM) User Manual
Page 10: Check/adjust water level

Auto Drain & Flush Valves
(when provided by Manufacturer)
Assm.
Number
Mfg.
Part
Number
ASCO
Part
Number
Solenoid
Type
De-Energized
Position
Diameter
Qty.
852178
461262
8210G2
Supply
Closed
1/2 inch
(12.7 mm)
1
461263 8262G262
Supply
Line
Drain
Open
1/4 inch
(6.35 mm)
1
461264
8210G35
Sump
Drain
Open
3/4 inch
(19.05 mm)
1
Part numbers subject to change.
IMPORTANT
The supply line should be of adequate size and
pressure to resupply the amount of water lost due to
bleed-off and evaporation. The drain line should be
the same size or larger than the supply line.
CAUTION
All solenoid valves and traps must be installed
below the roof to protect the supply water line from
freezing. If they cannot be installed below the roof,
an alternative method must be used to protect the
lines from freezing.
IMPORTANT
The supply solenoid (Valve A) is NOT the same as
the drain solenoids (Valve B and Valve C). Make sure
to use the proper solenoid for each location. Check
your local code requirements for proper installation
of this type of system.
1. Install the Water Supply Line
Supply line opening requirements vary by unit size
and arrangement and are field-supplied. Connect the
water supply line to the float valve through the supply
line opening in the evaporative cooling unit. Install the
1/2 in. normally closed solenoid (Valve A) in the supply
line. Install the 1/4 in. normally open solenoid (Valve B)
between the supply line and the drain line. Refer to
Auto Drain and Fill Evaporative Piping drawing shown
on this page.
2. Install the Drain Line
Connect an unobstructed drain line to the sump drain
overflow connection. Install the 3/4 in. normally open
solenoid (Valve C) between the sump drain connection
and the drain line.
A trap should be
used to prevent
sewer gas from
being drawn into the
unit. Refer to drain
trap drawing.
3. Check/Adjust Water Level
Check the water level in the sump tank. The water
level should be above the pump intake and below the
overflow. Adjust the float as needed to achieve the
proper water level.
6 in. min.
6 in. min.
Drain
Trap
Auto Drain and Fill Evaporative Piping
Installation Evaporative Cooler
Piping (optional)
continued
Evaporative Cooling with Auto Drain and Fill
Sump Overflow
Trap
Drain Line
Sump Drain
Supply Line
VALVE A
Supply Solenoid
(normally closed)
VALVE C
Sump Drain Solenoid
(normally open)
VALVE B
Supply Line Drain Solenoid
(normally open)
Model DG / DGX Pilot Ignition Make-Up Air
10
®