3.4.2 Snap the nosecone into position over the outside edges of the blade hub.
3.4.3 Make sure all three edges of the nosecone snap over the edge of the blade hub. After

installation tug on the nosecone to make sure it is securely attached.

3.5

Fish the wires into the unit and connect them to the battery – Use the existing pull wire

and attach the solar panel, wind generator and antenna wires to pull down into the unit. Once

the wires are into the unit, separate them. Attach the supplied forks to each black and red wire.

The green wire should be attached to the existing ground lug on the bottom of the panel. One

set of wires will have white electrical tape approximately 8-10 inches from the end. These are

the solar panel wires.

3.6

Attach the solar panel wires – Connect the red wire to the solar charge controller on the

positive (+) lug and the black wire on the negative (-) lug. These lugs are under the sunshine

icon (See

Figure 3).

3.7

Attach the wind generator wires – Connect the

red wire to the center screw terminal on the stop switch.

Connect the black wire to the same screw terminal the

existing black wire is connected to (See

Figure 3).

3.7.1 When the stop switch is pushed towards the panel

the unit is in charging mode.
3.7.2 When the stop switch is centered, it is not charging

and the blades are in a free spin mode.
3.7.3 When the stop switch is pulled toward the access

door, the blades will stop for maintenance.

4.0 INSTALL THE BATTERIES

NOTE:

Batteries must be FULLY bench charged before installation.

WARNING: Reversing the battery wires (reversed polarity) will cause damage to the solar charge

controller, wind generator GSM and IP wireless circuits and is NOT covered by the warranty.

4.1

Place the batteries into the unit – Insert the battery shelf plates into the bottom access door.

One battery should be placed on each shelf.

4.2

Connect the wires – Connect the large gauge wires with yellow rings to the bottom battery

along with the smaller gauge blue ringed wires. Connect the red wires to the positive (+) lugs

on the batteries, then connect the black wires to the negative (-) lugs. Install the second bat-

tery shelf plate and insert the top battery. Connect the small gauge yellow ringed wires to the

battery. Connect the red wire to the positive (+) lugs on the batteries, then connect the black

wire to the negative (-) lugs (See

Figure 4).

5.0 INSTALLING THE GSM CELLULAR UNIT

NOTE:

A local cellular dealer must provide a SIM card before it can place calls.

5.1 Installation
5.1.1 Remove the GSM unit from its shipping box.