INSTALLATION

4.2 Mounting

i

Install the Systempro control unit near the hydraulic
module to facilitate system commissioning.

• Consult the corresponding installation manual and install the

following elements:
- the heat pump,
- the hydraulic module,
- the Systempro control unit,
- the Climapro2 wireless room thermostat,
- the wireless outdoor sensor.

5 Hydraulic

connection

• Take care to clean the pipes before assembly removing any

debris or burrs. Grease and oils may need to be removed
they are not possible to remove by cleansing and fl ushing.
Foreign bodies in the system may enter the appliance and
interrupt its operation.

• Do not use any solvent products, due to the risk of damaging

the circuit.

• Only use original seals supplied with the appliance.

• Check that there are no leaks. Repair if necessary.

5.1

Heat pump circuit

• Comply with the values given in the table below when

making the hydraulic connections of the heat pump circuit.

Linear distance (without elbows or

additional pressure drops)

Min. diameter of tubes to

be installed

≤ 20 m

Ø ¾"

≤ 30 m

Ø 1"

b

In the case of an installation with the domestic
hot water tank option, deduce the pressure drop
of the 3-way valve with respect to the max. linear
distance allowed between the domestic hot water
tank and the PAC + between the PAC and the
hydraulic module (see chapter "Connection of an
exchanger tank for domestic hot water").

5.1.1

Connection to the heat pump

b

Insulate the pipes with an UV- and high-
temperature-resistant insulation.

1m min.

4

2

1

3

5

6

7

8

key
1 Heat

pump

fl ow circuit ¼ turn shut-off valve in the direction of

the building (not included)

2

Return circuit ¼ turn shut-off valve in the direction of the heat
pump (not included)

3

Return circuit hose in the direction of the heat pump (not
supplied)

4 Cap
5

Return connection (Ø1 ") to the heat pump

6

Flow heat pump connection (Ø1 ") to the building

7

Flow heat pump circuit hose in the direction of the building
(not supplied))

8

Insulation (not supplied)

• Remove the protection caps (4) located on the connections.

• Connect a hose (3) and a shut-off valve (2) to the return

connection (5) to the heat pump.

• Connect a hose (7) and a shut-off valve (1) to the fl ow heat

pump connection (6) in the direction of the building.