Dig

Use boom/swing control and bucket/dipper control to dig hole or trench.

Keep dipper and boom at right angles as
much as possible for maximum power.

Keep bucket in line with dipper as much
as possible.

Position bucket so teeth cut soil. As soil is
cut, curl bucket under dipper.

Move dipper and bucket together.
Increasing engine speed will not increase
backhoe force.

Move Unit

1.

Raise stabilizers.

2.

Release parking brake.

3.

Use remote ground drive switch to move unit.

4.

Lower stabilizers.

5.

Set parking brake.

IMPORTANT: For more information about backhoe controls, see page 48.