To set up the disk mill, you need a crane or a different suitable transport
device as well as 2 harnesses (not included in the scope of delivery) that
are at least 40 cm long and have a capacity of 500 kg.
CAUTION!
The weight of the disk mill is approx. 260 kg with grinding
disk and transport palette.
NOTICE!
Place the disk mill on a flat, stable surface. It may be
screwed to this or a base plate.
1.
The disk mill is screwed from below to the transport palette using
3 screws. Loosen the screws with a spanner (17 mm).
2.
Open the housing cover (14) by releasing the quick release screws
(X) attached on both sides.
3.
Once the quick release screws are loosened, pull the cover (14)
back a few centimetres and then lift it off.
4.
Two eyelets for attaching the harnesses can then be seen.