FG-3156

FG-3155

FG-2145

LEAVE FRONT OF DOOR JAMB

CLEAR OF SEALANT FOR DRAINAGE

SUB-SILL IS BED IN

SEALANT AT DOOR JAMB

RUN SEALANT MINIMUM 1"

ABOVE BACK OF SUB-SILL

NOTES:
1) USE SHEAR BLOCKS AS SHOWN IN FRAME ASSEMBLY SECTION OF THIS MANUAL TO SECURE HORI-
ZONTALS TO TUBULAR FRAMES.

2) DOOR FRAME IS ANCHORED BY FASTENERS THROUGH THRESHOLD AND DOOR FRAME HEADER.

3) DO NOT FABRICATE STANDARD 2 PIECE POUR & DEBRIDGED FRAME EXTRUSIONS FOR DOOR
FRAMES. IF THERMAL FRAME IS REQUIRED,OPTIONAL THERMAL DOOR FRAME FG-3389 OR FG-3444
MAY BE USED IN CONJUNCTION WITH THERMAL DOORS.

4) WHEN USING THE CENTER SET SYSTEM, THE TWO-PIECE OR TUBULAR FRAMING OPTION ARE AVAIL-
ABLE AS SHOWN ABOVE. WHEN USING EITHER THE FRONT SET OR BACK SET SYSTEM ONLY
THE TUBULAR OPTION IS AVAILABLE. THE VERTICAL FOR THE FRONT OR BACK SET OPTIONS IS FG-
3287.

DOOR FRAME INSTALLATION

1"

50






S E R I E S 3 0 0 0 T H E R M A L M U L T I P L A N E I N S T A L L A T I O N M A N U A L