Series 5600 Silicone Structural Glazed Installation Instructions

Section VI: Glazing Preparation

Air Seal at Expansion Joint

Clean

A.)

Clean all metal and infill that will contact silicone with proper cleaner, and then

apply silicone primer, if required, as recommended by silicone sealant manufacturer.

Setting Blocks

A.)

1” Glazing & ¼” Glazing - Position and install setting blocks as directed on

“APPROVED” shop drawings.

Install air seal at

expansion joint.

Splice Sleeve

Joint Plug

Expansion Joint

Note: At corners, use more than one air

seal as required. Miter to fit corner.

Note: SSG Vertical Splice Locations EFCO
recommends that Vertical Splice Line should
be below the Intermediate Horizontal
Member, this will Minimize Shear Stress at

the Structural Seal Line.