EFCO CORPORATION 6/2012 PART NO. Y557

27

Series 5500 Advanced & Alternate Installation Instructions

Section V: Vertical Splice Joints

STEP #3 CRITICAL MULLION SEAL AT SPLICE

A. Insert the 1/4” x 1” x 5” long foam caulk joint backer as shown below leaving 1” of

the backer extending above the top of the mullion.

B. Apply sealant between the thermal struts, starting where the notch in the mullion

begins at the exterior cover, sealing the space to the top of the mullion as shown.

C. Tool the sealant flush with the face of the notch of the thermal struts.

1/4” X 1” X 5”

FOAM CAULK

JOINT BACKER

MULLION SPLICE SLEEVE

LOWER MULLION

SPLICE ATTACHMENT

SCREWS (cap seal)

Seal the gap between the

thermal struts including

the void at the bottom of

the notch.