beautypg.com

Heavy-duty anchor connections) – EFCO S5500 Advanced User Manual

Page 13

background image

EFCO CORPORATION 6/2012 PART NO. Y557

13

Series 5500 Advanced & Alternate Installation Instructions

‘M’ ANCHOR

‘M’ ANCHOR

‘F’ ANCHOR

DEAD LOAD

SHIMS

ANCHOR BOLTS

AS REQ’D.

ANCHOR BOLTS

AS REQ’D.

PRE-ASSEMBLED

FRAME UNIT

SHEAR BLOCKS FOR

DROP ON SILL

SHEAR BLOCKS FOR

DROP-ON HEAD

‘F’ ANCHOR

Section III: Alternate Anchorage Method

(Heavy-Duty Anchor Connections)

STEP #2 INSTALL FRAME COMPONENTS

A. Set the frame with ‘F’ and ‘M’ anchors into the opening. Adjust the frame’s position to place it

in the proper position with regard to established benchmarks.

B. Using dead load shims under each vertical mullion, level the frame and set it to the appropriate

elevation as indicated in the approved shop drawings.

C. After the frame is plumb and all adjustments have been made, match drill through the holes in

the ‘F’ and ‘M’ anchors into the surrounding substrate, and apply the appropriate anchor bolts.

Anchor bolt size, type, quantity, and location vary. Refer to the approved shop drawings for

more information. Anchor bolts should be installed per the recommendations of the bolt

manufacturer.

D. Apply the shear blocks to the top and bottom of the mullions as shown in the approved shop

drawings.