Install components – Great Plains NP3000A Predelivery Manual User Manual
Page 20

407-613Q
03/31/2011
16
NP3000
Great Plains Manufacturing, Inc.
Install Components
Crushing and Machine Damage Hazards:
“Prepare Hydraulics” beginning on page 14, must be
completed prior to most topics in this section. Hydraulic lines
may not be charged prior to shipment. Operating systems with
air in the lines could result in jerky movements and sudden
falls of frame or wings. Anyone nearby could be seriously
injured or killed. Machine damage is likely.
Not all topics of this manual section will apply to the
implement at hand. Each topic includes a continue-at
instruction if the topic does not apply, and may end with a
further continue-at instruction if the next topic would not
apply, based on the current topic.
Loss of Time Risk:
Install in order. To ensure safety and reduce effort, the topics
must be completed in the order presented. Later topics rely on
earlier topics having been completed. Some steps cannot be
performed at all if required prior steps are not yet completed.
Before beginning installation steps:
• the implement is presumed to be unloaded from the
trailer,
• the hydraulic systems are presumed to be charged
and safe to operate, but
• the implement is not presumed to be folded or
unfolded.