INSTALLATION
3-2
Manual 0-2690
2. Remove the tape securing the shield of the torch leads
to the leads.
3. Unfold the shield towards the end of the leads.
4. Feed the Control Cable through the boot on the end of
the Arc Starter Box.
5. Feed the torch leads through the boot on the torch end
of the Arc Starter Box.
A-01775
Torch Leads
Hose Clamp
Shield Braid
Torch Leads
Shield Assembly
(Brass Hub)
Control Cable
Figure 3-2 Hose Clamp
6. Feed the Control Cable and torch leads through the
supplied Hose Clamp.
7. Connect the Control Cable to the mating connector on
the Center Chassis.
Control Cable
Control Cable
Connector
A-01774
Figure 3-3 Control Cable Connection
8. Connect the torch leads connectors to the bulkhead
connections per the following figure.
A-01776
Torch Leads
Secondary Gas
Plasma Gas
(Left-Hand Thread)
Coolant Supply
Coolant Return
(Left-Hand Thread)
Pre-Flow (N2)
Gas
Figure 3-4 Torch Leads Connections
9. Pull the shielding braid towards the end panel as far as
it will go up and over the brass hub. The hub is part of
the Boot Assembly and provides the grounding point
for the shielding in the torch leads.
NOTE
The shielding braid must not make contact with
the four mounting studs.
Torch Leads
Shield Braid
Torch Leads
Shield Assembly
(Brass Hub)
A-01777
Mounting
Stud
Figure 3-5 Shield Braid Installation