beautypg.com

3 start-up, 1 initial start-up, Initial start-up – Metrohm 850 Professional IC Anion MCS Gradient User Manual

Page 75

background image

■■■■■■■■■■■■■■■■■■■■■■

3 Start-up

850 Professional IC –Anion – MCS – Gradient

■■■■■■■■

65

3 Start-up

The chapter Start-up is divided into 2 sections:

Initial start-up

The initial start-up is carried out during the ini-
tial installation
.

Conditioning

Conditioning is carried out as a final installation
step and each time after the system is started.

3.1

Initial start-up

The initial start-up is carried out during the initial installation. The entire
system is flushed before guard column and separation column are instal-
led.

Caution

The separation column and guard column may not be installed for the
initial start-up.

Make sure that the 6.2744.040 coupling is being used instead of the
columns.

Perform the following steps during the initial start-up:

1 Preparing the software

Start the PC program MagIC Net.

Open the Equilibration tab in MagIC Net.

Select (or create) a suitable method.

2 Preparing the instrument

Ensure that the eluent aspiration tubing is immersed in the eluent
and that there is enough eluent in the eluent bottle.

Switch on the instrument.

3 Deaerating the high pressure pump

Deaerate the high pressure pump(s) via the purge valve (see
Chapter 2.10.2, page 34)
.